【单选题】

there are two major types of reserves used on projects. the (    ) is for (usually major) scope changes that were not considered as part of
the original plan, whereas the (    ) is to compensate for minor changes in estimating, escalation factors.
  • A.management reserve, unplanned allowance fund.

  • B.management reserve, contingency.

  • C.contingency fund, management reserve.

  • D.unplanned allowance fund, budgetary reserve.

  • E.unplanned reserve, planned reserve.

参考答案

查看答案

相关试题

单选题 a(n) (    ) system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight,
storage and loss.
查看答案
单选题 two sources of variation in the length of hex bolts exist. production variation and measurement error. the qc manager knows that the
standard deviation from these sources is 0.24" and 0.43" , respectively. what is the total standard deviation.
查看答案
单选题 a deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as: 查看答案
单选题 which of the following terms refers to the situation where the work is being used for the purpose intended and so certified: 查看答案
单选题 a (    ) estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%). 查看答案
单选题 for communication to occur, there must be: 查看答案
单选题 which of the following activities can be considered as part of risk mitigation 查看答案
单选题 a line manager possesses information which the project team needs, but withholds the information. the results in a(n): 查看答案
单选题 guidelines for estimating time durations include: 查看答案
单选题 one of your project team members has made a technological breakthrough on an r & d project. the result will be new business for the
company, as well as a company patent. the team member received a company bonus. the motivational strategy used here is:
查看答案
单选题 assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource (    ). 查看答案
单选题 affinity diagrams are used to: 查看答案
单选题 the most common form of written project communication is 查看答案
单选题 the financial closeout of a project dictates that: 查看答案
单选题 which of the following utility functions reflects risk-aversion: 查看答案
单选题 which of the following scheduling methods uses more of the risk management concepts: 查看答案
单选题 non-verbal communication includes: 查看答案
单选题 statistical cost estimating techniques (based upon history), are called (    ) estimates and are a (    ) approach. 查看答案
单选题 which of the following is not part of contract administration 查看答案
单选题 the term that best describes the 'right' to manipulate or change others is called? 查看答案