assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource (    ).
  • A.allocation.

  • B.partitioning

  • C.leveling

  • D.quantification.

  • E.none of above.

参考答案

查看答案

相关试题

单选题 which of the following activities can be considered as part of risk mitigation 查看答案
单选题 in general, attempts to smooth out period to period resources will (    ) the scheduled time and (    ) project costs. 查看答案
单选题 two sources of variation in the length of hex bolts exist. production variation and measurement error. the qc manager knows that the
standard deviation from these sources is 0.24" and 0.43" , respectively. what is the total standard deviation.
查看答案
单选题 there are two major types of reserves used on projects. the (    ) is for (usually major) scope changes that were not considered as part of
the original plan, whereas the (    ) is to compensate for minor changes in estimating, escalation factors.
查看答案
单选题 which of the following is not part of contract administration 查看答案
单选题 risk management methodology should be adhered to in: 查看答案
单选题 which of the following scheduling methods uses more of the risk management concepts: 查看答案
单选题 the most common form of written project communication is 查看答案
单选题 the ability to get an individual or group to perform a given task is best described as: 查看答案
单选题 which of the following utility functions reflects risk-aversion: 查看答案
单选题 herzberg identified factors which, if present, will lead to increased motivation. a typical factor would be: 查看答案
单选题 a(n) (    ) system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight,
storage and loss.
查看答案
单选题 statistical cost estimating techniques (based upon history), are called (    ) estimates and are a (    ) approach. 查看答案
单选题 expectancy theory as applied to project management implies that: 查看答案
单选题 which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous
element has been completed?
查看答案
单选题 the rule of seven used by quality control engineers states that if a run of seven or more samples lays on one side of the process mean, then
the process is out of control. what is the probability that this condition is the result of random variations.
查看答案
单选题 affinity diagrams are used to: 查看答案
单选题 a deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as: 查看答案
单选题 a (    ) estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%). 查看答案
单选题 assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource (    ). 查看答案