【单选题】

overlapping activities on a project, such as design and construction, is referred to as:
  • A.fast tracking

  • B.risk conversion.

  • C.parallel management.

  • D.process improvement.

  • E.synchronous manufacturing

参考答案

查看答案

相关试题

单选题 which of the following statements about the cost of quality are true? 查看答案
单选题 a project manager trying to communicate accurately to the team should use: 查看答案
单选题 japanese quality control has improved dramatically in the last 30 years for all of the following reasons except: 查看答案
单选题 which of the following processes allow an unsuccessful bidder to seek remedy for contract award to another bidder. 查看答案
单选题 it is argumentative whether project managers actually control costs. which of the following is the most common element over which the
project manager may have some degree of control?
查看答案
单选题 the major reason why a project manager would use written instead of oral communication is: 查看答案
单选题 an advertiser who uses a movie or sports star to endorse a product is trying to use power. 查看答案
单选题 a project team member submits a suggestion on how to improve the corporate procurement process. this is an example of (    )
communication
查看答案
单选题 the wbs is: 查看答案
单选题 the scope management provides: 查看答案
单选题 overlapping activities on a project, such as design and construction, is referred to as: 查看答案
单选题 the "buy or make" decision is usually made during the: 查看答案
单选题 during project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two
other projects. the best way to handle this problem would be to:
查看答案
单选题 back charges refers to: 查看答案
单选题 according to herzberg, which of the following is a motivational factor? 查看答案
单选题 the pareto principle is a technique used to determine which quality control problems in a particular process should be corrected. which of
the following statements best represents the philosophy employed by this principle?
查看答案
单选题 including the customer in the process of project planning is: 查看答案
单选题 which of the following actions is an example of risk response: 查看答案
单选题 communication in both project and non-project-driven organizations should occur in directions. 查看答案
单选题 monte carlo simulation: 查看答案