【单选题】

the scope management provides:
  • A.a basis for future decisions about the project.

  • B.a baseline to accomplish verification measures.

  • C.a baseline to evaluate potential scope changes.

  • D.all of the above.

  • E.b and c only.

参考答案

查看答案

相关试题

单选题 most quality problems: 查看答案
单选题 the major reason why a project manager would use written instead of oral communication is: 查看答案
单选题 which of the following statements about the cost of quality are true? 查看答案
单选题 company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the: 查看答案
单选题 which method shown below is acceptable for reducing cost or shortening the schedule? 查看答案
单选题 the scope management provides: 查看答案
单选题 a comparison of completion status to baseline is referred to as (    ). 查看答案
单选题 a computer tape which contains historical project information is called (    ) tape. 查看答案
单选题 during project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two
other projects. the best way to handle this problem would be to:
查看答案
单选题 communication in both project and non-project-driven organizations should occur in directions. 查看答案
单选题 japanese quality control has improved dramatically in the last 30 years for all of the following reasons except: 查看答案
单选题 job descriptions are examples of (    )communications. 查看答案
单选题 according to herzberg, which of the following is a motivational factor? 查看答案
单选题 a line manager who is asked to wear two hats and function as a project manager at the same time is likely to exercise: 查看答案
单选题 the most effective means of determining the cost of a project is to price out the (    ). 查看答案
单选题 an advertiser who uses a movie or sports star to endorse a product is trying to use power. 查看答案
单选题 monte carlo simulation: 查看答案
单选题 job continuity would be an example of (    ) in maslow's hierarchy of needs. 查看答案
单选题 giving a part of project work to a contractor is an example of: 查看答案
单选题 the logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to
as:
查看答案